FERC sustains incentives for 222-mile Kammer Juniata transmission line on rehearing

  • Pennsylvania consumer advocate's rehearing arguments fail to change outcome
  • 765 kV line has estimated $1.7 billion cost, Kammer says
  • Incentives include 100% construction work in progress in rate base
Illustrative photo: power transmission linesPhoto: Wikimedia Commons - Wiremu Stadtwald Demchick, CC BY 4.0
Illustrative photo.

Republish

The full contents of the HTML code must be used as is, not changed or edited.

— The Federal Energy Regulatory Commission (FERC) on Nov. 19 sustained transmission rate incentives for Kammer Juniata Transmission, LLC's 222-mile, 765 kV line after addressing rehearing arguments from the Pennsylvania Office of Consumer Advocate (OCA), modifying the discussion in its July order.

The project would run between the Kammer substation in West Virginia and the Juniata substation in Pennsylvania. Kammer said the total estimated cost is $1.7 billion and the line is expected to go into service in June 2031, according to the order in Docket No. ER26-1734-002.

The incentives, effective July 11, 2026, include recovery of 100% of prudently incurred costs if the project must be abandoned for reasons outside Kammer's control, and inclusion of 100% of construction work in progress in rate base. They also include a hypothetical capital structure of 60% equity and 40% debt until the project is placed into service. FERC also conditionally granted a 50-basis-point adder to Kammer's return on equity.

OCA argued that FERC applied the wrong reliability standard, that PJM Interconnection, L.L.C. (PJM) did not select the project through a "fair and open" process, that FERC ignored load forecasting issues, and that FERC denied OCA due process by not setting the reliability issue for hearing.

FERC said the record indicates the project was selected through a fair and open planning process, noting PJM received 134 proposals from 19 different entities. The order said that, in these circumstances, the difference between "enhance" and "ensure" reliability is "a distinction without a difference."

According to the order, OCA's claims that PJM departed from its Operating Agreement and its broader challenges to PJM's load forecast are better addressed in a separate complaint under section 206 of the Federal Power Act.

FERC said it is addressing speculative and duplicative transmission service requests for large loads in Docket No. EL26-67-000.

Kammer is a wholly owned subsidiary of NextEra Energy Transmission, LLC. The PJM Board selected the project on Feb. 12, 2026. FERC accepted Kammer's request on July 10, 2026, and OCA sought rehearing on Aug. 7.