FERC approves gas projects in four orders, including Sabine Pass LNG expansion
- Forza pipeline to carry up to 750,000 Dth/d in New Mexico, Texas
- Three new liquefaction trains approved at Louisiana LNG terminal
- Forza and Texas Eastern certificates stayed during rehearing period
Photo: Unsplash - JJ YingUpdated Nov. 19.
WASHINGTON, Nov. 19 — The Federal Energy Regulatory Commission (FERC) on Nov. 19 approved, in four separate orders, a liquefied natural gas (LNG) storage plant in Virginia, three liquefaction trains at Louisiana's Sabine Pass LNG Terminal and new pipelines in Mississippi, New Mexico and Texas.2,3
In Docket No. CP26-20-000, FERC issued a certificate to Columbia Gas Transmission for its Southeast Virginia Energy Storage Project in Sussex County, Virginia.3 The project includes the new Waverly Energy Storage Facility and about 5,398 feet of 12-inch-diameter pipeline.3 Columbia estimates its total cost at about $384 million, according to the order.3
The order said the project will enable Columbia to provide up to 10,000 dekatherms per day (Dth/d) of liquefaction capacity, 1,100,000 Dth of storage capacity and 120,000 Dth/d of firm vaporization and sendout capacity.3 Columbia has a 20-year precedent agreement with Virginia Natural Gas, Inc. for 100% of the project's firm storage capacity.3 No party opposed the application.3
According to the order in Docket Nos. CP24-75-000 et al., the Sabine Pass LNG Expansion Project would raise the terminal's maximum LNG production capacity, measured in billion cubic feet per year (Bcf/y), by 950.0 Bcf/y, or 19 MTPA, to 2,611.94 Bcf/y.1 The same order certifies Sabine Crossing's pipeline project, which Sabine Crossing estimates will cost about $1.626 billion, and Creole Trail's expansion project, which Creole Trail estimates will cost $390,269,433.1
The Sierra Club protested the Sabine Pass project.1 FERC said the group's allegations did not amount to the showing needed to overcome the presumption in favor of authorization under the Natural Gas Act.1
In Docket No. CP26-75-000, FERC certified Texas Eastern Transmission's Line 31 Expansion Project, estimated to cost $131,000,000.2 The project would provide 125,000 Dth/d to Entergy Mississippi's proposed Traceview Advanced Power Station.2
In Docket Nos. CP26-34-000 and CP26-35-000, FERC issued certificates to Forza Pipeline LLC for about 35.94 miles of 36-inch-diameter pipeline from Lea County, New Mexico, to Winkler County, Texas.4 The pipeline is designed to provide up to 750,000 Dth/d of firm transportation service.4 Forza estimates the cost at approximately $183,096,905, according to the order.4
Forza has precedent agreements with Targa Gas Marketing, an affiliate, and Devon Energy Corporation for approximately 87% of the capacity.4 Under the order, Forza will also lease 750,000 Dth/d of capacity on Bull Run Pipeline LLC's intrastate Bull Run Extension for a monthly fee of $2,281,250, with a 10-year primary term.4
The Haley Family, a group of landowners, protested and argued that Forza had not shown a need for the project.4 FERC said the precedent agreements were sufficient to show need.4
FERC stayed the Texas Eastern and Forza certificates during the 30-day rehearing period.2,4 The orders said landowners had intervened and protested in both cases, Kevin J. Robinson for Line 31 and the Haley Family for Forza, and neither company has yet acquired all necessary property interests.2
The Columbia facilities must be in service within four years of the order, the Sabine Pass facilities within 10 years, the Line 31 facilities within three years and the Forza facilities within two years.1,3,4 Sabine Pass said it anticipates that LNG exports from the expansion could begin as soon as 2030.1