FERC approves Mountain Valley's MVP Boost project for up to 600,000 Dth/d

  • New Virginia compressor station, upgrades at three West Virginia sites
  • Shippers contracted all project capacity, FERC says
  • Swann station construction requires Virginia air permit first
Illustrative photo: a pipelinePhoto: Unsplash - Quinten de Graaf
Illustrative photo.

Republish

The full contents of the HTML code must be used as is, not changed or edited.

What changed The certificate authorizes added compression that raises the Bradshaw Compressor Station's total from 93,880 HP to 117,350 HP, the Harris Compressor Station's from 41,000 HP to 93,500 HP and the Stallworth Compressor Station's from 41,000 HP to 93,880 HP.

— The Federal Energy Regulatory Commission (FERC) issued a certificate on Nov. 19 authorizing Mountain Valley Pipeline, LLC to build its MVP Boost Project, which is designed to provide up to 600,000 dekatherms per day of additional firm natural gas transportation service.

The project includes a new Swann Compressor Station in Montgomery County, Virginia, and added compression at three existing compressor stations in Wetzel, Braxton and Fayette counties, West Virginia, according to the order in Docket No. CP26-14-000. Mountain Valley estimates the total cost at approximately $503,490,246.

Shippers contracted all project capacity (dekatherms per day)

Duke Energy Carolinas, LLC contracted for 275,000 dekatherms per day, Virginia Power Services Energy Corp., Inc. for 200,000 and Public Service Company of North Carolina, Inc. for 125,000, FERC said. FERC said these precedent agreements for 100% of the capacity support a finding of need. It found market studies on data center demand cited by the Southern Alliance for Clean Energy unpersuasive.

An environmental assessment issued Aug. 7, 2026, concluded that approving the project would not constitute a major federal action significantly affecting the quality of the human environment. Staff could not determine whether the effects of the project's greenhouse gas emissions would be significant or insignificant, according to the order.

Commenters noted that the Virginia Department of Environmental Quality had paused processing Mountain Valley's air permit application for the Swann station. FERC declined to delay its decision. Under the order, Mountain Valley must file proof that it has received a Clean Air Act permit before building that station.

FERC approved Mountain Valley's use of its existing Mainline System rates as the maximum recourse rates for the project. It also granted a presumption of rolled-in rate treatment, absent a significant change in circumstances.

Mountain Valley must complete construction and make the facilities available for service within two years of the order. It must also file noise surveys no later than 60 days after placing the stations in service.

Mountain Valley filed its application on Oct. 23, 2025.