  • RISE St. James, Sierra Club challenge state air permit
  • Petition alleges no environmental justice analysis was done
  • Groups seek reversal of Oct. 26 permit decision
Illustrative photo: a courthousePhoto: Wikimedia Commons - Jeffrey Beall, CC BY 4.0
Illustrative photo.

Republish

The full contents of the HTML code must be used as is, not changed or edited.

— RISE St. James Louisiana and Sierra Club asked a Louisiana court on Nov. 20 to vacate an air permit for a Hyundai-POSCO steel plant, alleging the Louisiana Department of Environmental Quality (LDEQ) issued it without an environmental justice analysis.1

The petition for judicial review, filed in the 19th Judicial District Court for the Parish of East Baton Rouge, challenges LDEQ's Oct. 26, 2026, decision.1 That decision granted Prevention of Significant Deterioration Permit PSD-LA-872 and Part 70 Operating Permit 0180-00243-VO to Hyundai-POSCO Louisiana Steel LLC for an integrated iron- and steelmaking plant in Ascension Parish.1

According to the petition, the permit authorizes 1.6 million tons per year of greenhouse gas emissions, 824 tons per year of nitrogen oxides and 366 pounds per year of mercury, among other pollutants.1

The groups allege that LDEQ did not assess any environmental costs in its cost-benefit analysis.1,2 They also allege the agency released its public-trust analysis only in its final decision, after the comment period had closed.2 The petition says Hyundai removed an environmental justice analysis from its application in a May 27, 2026, addendum without explanation.1

The petition also challenges LDEQ's reliance on the Dutchtown ozone monitor rather than the closer Carville monitor.1,2 The petitioners allege that LDEQ's best available control technology analysis did not evaluate electrified equipment or incremental green-hydrogen blending case by case.1

"LDEQ has failed to perform the most basic function of its role and deprived the community of a transparent, thorough, and accurate assessment of the facility’s potential negative impacts," Sierra Club Senior Attorney Andrea Issod said in a statement.2

In its final decision, LDEQ found that "The social and economic benefits of the HPLS Steel Mill will outweigh its potential adverse environmental impacts," according to the petition.1

The groups ask the court to reverse the decision, vacate the permits and remand the matter.1

Hyundai applied for the permit on Dec. 23, 2025, according to the petition.1 LDEQ held a public hearing on Sept. 1, 2026, and the comment period ended on Sept. 15, 2026.1