NRC order makes TRISO-X weld corrective actions binding at Oak Ridge site
- Order resolves apparent violation found in March inspection
- NRC agrees not to issue violation notice or penalty
- Weld demonstration due within 30 days of order
Photo: Unsplash - Jametlene ReskpWASHINGTON, Nov. 13 — The U.S. Nuclear Regulatory Commission (NRC) has issued a confirmatory order to TRISO-X, LLC that makes legally binding the company's commitments to resolve an apparent violation involving welds in a building under construction at its Oak Ridge, Tennessee, site.
The order was issued Oct. 21 and took effect on issuance. It follows mediation sessions on July 29 and Aug. 20, 2026, according to the NRC notice in Docket ID NRC-2026-5050. TRISO-X consented to the order on Oct. 5 and waived its right to a hearing.
The NRC inspected construction from March 9 through 12, 2026. According to the order, the inspection identified an apparent violation tied to TRISO-X's failure to apply effective design control measures to ensure the design basis supporting the structural stability function of the TX-1 process building's main force resisting system was maintained during construction.
The NRC said in the order that the company approved welding processes that did not achieve the weld size the construction code required. It also said required inspections of diagonal brace welds were not done during periods between approximately Jan. 28 and March 10, 2026.
In return for the commitments, the NRC agreed not to issue a notice of violation or impose a civil penalty, the order says.
Under the order, TRISO-X must make available to the NRC within 30 days a demonstration that the existing braced-frame intersection welds meet code requirements, except for components it chooses to rework or replace. If the NRC concludes it did not, the company must repair, replace or redesign all of those welds within six months of the NRC correspondence documenting that conclusion.
Other commitments include training, external benchmarking within 12 months and a lessons-learned presentation at the March 2027 NRC Regulatory Information Conference, or another agreed forum if that conference is not available.
Any person adversely affected, other than TRISO-X, may request a hearing within 30 calendar days of the order's issuance.
The NRC issued the license for the facility, License No. SNM-7007, on Feb. 13, 2026. It notified TRISO-X of the inspection results on June 9, 2026.