Energy Department orders Michigan coal plant available to meet emergency through February 2027

  • Emergency order covers J.H. Campbell plant in West Olive
  • Order runs Nov. 15, 2026, through Feb. 12, 2027
  • Order issued under Federal Power Act section 202(c)
Illustrative photo: a coal-fired power stationPhoto: Wikimedia Commons - Sebastian Koppehel, CC BY 4.0
Illustrative photo.

Republish

The full contents of the HTML code must be used as is, not changed or edited.

— The U.S. Department of Energy (DOE) on Nov. 13 issued an emergency order directing the Midcontinent Independent System Operator (MISO) and Consumers Energy to keep the coal-fired J.H.1 Campbell Generating Facility in West Olive, Michigan, available to operate to meet the emergency from Nov. 15, 2026, through Feb. 12, 2027.1

DOE Order No. 202-26-51, issued under section 202(c) of the Federal Power Act, also directs MISO to take every step to use economic dispatch only during the hours necessary to meet the emergency and to minimize costs for families and businesses, according to the order.1

In a press release on Nov. 14, DOE said the order addresses grid reliability issues in the Midwest and that the emergency conditions that led to the original order persist.2

"Ensuring coal plants such as the Campbell Plant are available to operate has prevented blackouts and likely saved lives," U.S. Secretary of Energy Chris Wright said.2

DOE cited a joint report from the Federal Energy Regulatory Commission, the North American Electric Reliability Corporation and its Regional Entities, saying events during the Winter 2026 Arctic Cold Period, including Winter Storm Fern, showed the need for dispatchable generation from facilities like the Campbell Plant.2

The plant was originally slated to shut down on May 31, 2025, 15 years before the end of its scheduled design life, according to the release.2